Skip to main content

Meeting Details

Date

November 15, 2025

Time

10:15 - 11:00

Location

Microsoft Teams (Online)

Attendees

All members present
Meeting called by: Phuc Vo Facilitator: Phuc Vo Note taker: Quynh Nguyen Timekeeper: Phuc Vo

Official Meeting Minutes Document

View full meeting minutes on SharePoint

Agenda Item: Check Progress

Presenter: Phuc Vo Review of completed architecture and design tasks from the previous sprint.

Completed Action Items

All assigned tasks from the previous sprint were successfully completed:
  • Architecture Design
  • Data Model
  • Infrastructure
Status: ✓ All Complete
  • C4 System Context - Viet Nguyen ✓
  • Draft C4 Backend Container - Viet Nguyen ✓
  • Draft C4 Backend Component - Viet Nguyen ✓
  • Draft C4 Frontend Container - Quynh Nguyen ✓

Agenda Item: Sprint Planning

Presenter: Phuc Vo Planning for the next sprint focusing on diagram refinement and implementation.

Assigned Tasks

Task: Review Diagram Description: Check Tuturuuu for assigned review tasks Assigned to: All members Deadline: November 18, 2025
Task: Setup Report Template Description: Initialize documentation template for milestone report Assigned to: Quynh Nguyen Deadline: November 18, 2025
Task: Refine Diagram(s) with Kubernetes Description: Add Kubernetes deployment to architecture diagrams Assigned to: BE team Deadline: November 19, 2025
Task: Refine C4 BE Description: Polish and finalize backend C4 diagrams Assigned to: BE team Deadline: November 19, 2025
Task: CI/CD GitHub Actions Description: Set up automated testing and deployment pipeline Assigned to: Viet Nguyen Deadline: TBD
Task: Implement Frontend Description: Check Tuturuuu for assigned frontend tasks Assigned to: FE team (Phuc Vo, Quynh Nguyen) Deadline: December 7, 2025
Task: Implement Backend Description: Check Tuturuuu for assigned backend tasks Assigned to: BE team (Viet Nguyen, Tung Nguyen, Ngoc Nguyen) Deadline: December 7, 2025

Task Summary Table

TaskAssigned ToDeadlineStatus
Review DiagramAll members18/11/2025In Progress
Setup Report TemplateQuynh Nguyen18/11/2025In Progress
Refine Diagram(s) with KubernetesBE team19/11/2025In Progress
Refine C4 BEBE team19/11/2025In Progress
CI/CD GitHub ActionsViet NguyenTBDPending
Implement FrontendFE team07/12/2025Pending
Implement BackendBE team07/12/2025Pending

Progress Highlights

Architecture Complete

All C4 diagrams (System Context, Container, Component) completed for both frontend and backend

Data Model Ready

Entity Relationship Diagram finalized and ready for implementation

Repository Initialized

GitHub repository set up with proper structure

Moving to Implementation

Team transitioning from design phase to active development

Key Decisions

Decided to enhance architecture diagrams with Kubernetes deployment strategy to meet Ultimo (Advanced) level requirements. Backend team responsible for this refinement.
Quynh Nguyen assigned to set up the report template for Milestone 1 submission. Template should follow the 30-page requirement format.
Viet Nguyen to implement GitHub Actions for automated testing and deployment. This will ensure code quality and streamline the development workflow.
Set December 7, 2025 as the target date for completing initial frontend and backend implementation. This provides buffer time before Milestone 2 deadline (January 13, 2026).

Sprint Objectives

Short-term (Nov 18-19, 2025)

  1. Complete diagram reviews
  2. Set up report template
  3. Refine diagrams with Kubernetes
  4. Polish C4 backend diagrams

Medium-term (Dec 7, 2025)

  1. Complete frontend implementation
  2. Complete backend implementation
  3. Set up CI/CD pipeline
  4. Integration testing

This meeting marked the transition from design phase to implementation phase, with all architecture and data model tasks successfully completed.

Next Steps

  1. Immediate: Review all diagrams on Tuturuuu
  2. This Week: Complete diagram refinements and report template
  3. Next 3 Weeks: Focus on frontend and backend implementation
  4. Ongoing: Daily standups to track progress
  5. December 7: Target completion for initial implementation