Overview
This section contains the official meeting minutes for the SGJM Team throughout the DEVision Job Manager project development.All meetings follow our bi-weekly sprint review cycle and daily standup
schedule. Meeting minutes are recorded by Quynh Nguyen and linked to
corresponding items on
Tuturuuu.
All Meeting Minutes
MM10 - Sprint 3 Review & Sprint 4 Planning
December 20, 2025 | 21:10 - 22:15 | DiscordReview Sprint 3 completion and planning for Sprint 4 implementation tasks.Key Topics: Sprint 3 review, FE revamp, BE security, Stripe payment integration, Kafka setup
MM9 - Progress Review with Dr. Tri Huynh
December 19, 2025 | 14:15 - 15:15 | RMIT SGS CampusOffline progress review with lecturer focusing on integration and deployment concerns.Key Topics: BE/FE integration, K8s deployment planning, Workload balance
MM8 - Sprint 3 Progress Review & Grooming
December 14, 2025 | 10:30 - 11:15 | DiscordReview Sprint 3 progress and grooming session for upcoming tasks.Key Topics: PR review practices, JA integration, Cloud deployment, BE integration
MM7 - Sprint 2 Review & Sprint 3 Planning
December 7, 2025 | 10:00 - 11:20 | DiscordReview Sprint 2 progress and comprehensive planning for Sprint 3 implementation tasks.Key Topics: Sprint 2 review, FE pages, BE APIs, SSO, Dockerization, Redis, Kafka
MM6 - Sprint Planning & Implementation Tasks
December 1, 2025 | 10:10 - 11:20 | DiscordProduct backlog decisions for upcoming sprint and implementation task assignment for Sprint #3.Key Topics: Product backlog planning, BE API assignment, FE Sprint #3 goals, Supabase setup
MM5 - Sprint Planning & Task Assignment
November 23, 2025 | 10:10 - 11:20 | DiscordProgress check, Sprint #2 backlog planning, and comprehensive report documentation task assignment for Milestone 1.Key Topics: Sprint #2 backlog, Report documentation assignment, Way of work review, JA Team coordination
MM4 - Progress Review
November 21, 2025 | 15:00 - 16:15 | RMIT SGS CampusOffline progress review with Dr. Tri Huynh focusing on ER Diagram and C4 Frontend Components.Key Topics: ER Diagram review, C4 Frontend Components review, Lecturer feedback
MM3 - Progress Review & Sprint Planning
November 15, 2025 | 10:15 - 11:00 | Microsoft TeamsProgress review of architecture design and planning for implementation phase. All design tasks completed successfully.Key Topics: Architecture completion, Kubernetes integration, Implementation planning
MM2 - Sprint Planning
November 10, 2025 | 21:30 - 23:10 | Microsoft TeamsTeam sprint planning meeting to establish structure and assign initial tasks. Migration to Tuturuuu platform.Key Topics: Team structure, Sprint cadence, C4 diagrams, ERD assignment
MM1 - Way of Work
November 7, 2025 | 16:50 - 17:10 | Microsoft TeamsInitial team meeting with Dr. Tri Huynh to establish way of work and project foundation.Key Topics: Scrum board setup, Task planning, Workspace organization
Meeting Guidelines
Documentation Standards
All meeting minutes must include:- Date, time, and location
- Meeting facilitator and note taker
- List of attendees
- Agenda items with presenters
- Action items with assignees and deadlines
- Special notes and conclusions
Meeting Types
- Daily Standup
- Sprint Planning
- Sprint Review & Retrospective
Time: 10:00 AM (weekdays)
Duration: 15 minutes
Platform: Discord
Purpose: Quick progress updates and blocker identification
Action Item Tracking
All action items from meetings are:- Recorded in meeting minutes
- Created as tasks on Tuturuuu
- Linked to corresponding meeting minute documents